STEP
1:
Start at ground level and ensure that the staring row is
level.
STEP 2:
Our
slots as required in stone cladding using a standard
biscuit cutter fitted with diamond cutting wheel. Always
cut slot measured from front face of panels to ensure
plumb/flush faces.
NOTE:
For correct loading of the StoneClip, the cut must be
made centrally in the top and bottom edges of the stone
panels (eg, 40mm stone to have the cur made 20mm from
the front edge).
STEP 3:
Mount
panel onto bottom brackets and inert StoneClips into
upper panel slots. Hold clip in place ensure centre
spindle sits on upper edge of stone panel.
STEP
4:
Drill into wall through top mounting hole of StoneClip.
Drive in zinc-alloy metal hit anchor pins using hammer
and punch to affix StoneClip.
It
is recommended to fill the slots in the top of the
panels with silicone sealer to take up any play in the
panels and to stop moisture pooling in the lot.
STEP
5:
Use
Nylon “X” spaces between panels to provide even spacing.
USING ADJUSTABLE STONECLIPS:
STEP 1:
Make
cut in panels with biscuit butter (as before) and indent
if panel is to be flush-fitted.
STEP 2:
Locate StoneClips with front face to wall and ser the
adjustment to exact size required. Then lock the nut in
place and remove StoneClip from panel and trim off the
excess thread.
STEP 3:
Reinstall StoneClip with locknut securely locked in
place and in forward position. Then drill hole in wall
for fixing pin through StoneClip fixing hole.
STEP 4:
Drive in zinc-alloy metal hit anchor pins using hammer
and punch to affix StoneClip. Check for plumb before
repeating process.
NOTE: To comply with building codes and engineers report
angle strip need to be affixed every 3 vertical metres.
Slot thickness to be no greater than 0.3mm wider than
the clip thickness.
DISCLAIMER: The StoneClips must be installed along
the lines of the Engineers Detail, including the installation of
angle restraints at each lift level and the use of the
right fixing restraints.
BACK TO TOP
|